State, contractor in dispute over firing range

Builder of police facility blames state for overruns

state denieS charges

May 25, 2000|By Mike Farabaugh , SUN STAFF

Problems with the rifle range are not the only ones at Maryland's new $4.6 million police firearms training center in Sykesville, where more fingers have been pointed than shots fired.

The state and the contractor at the center, EnviroServe Inc. of Sykesville, are in a dispute over who is responsible for what EnviroServe claims are $2.4 million in cost overruns, most of them associated with four pistol ranges.

The state's Department of General Services (DGS), which oversaw construction of the firearms training center, says EnviroServe worked too slowly. EnviroServe says it was slowed by poor design and changes before and after construction began.

Advertisement

The dispute is unlikely to be resolved until April, when the Maryland Board of Contract Appeals will hear testimony and settle the dispute.

The state will incur an additional, unexpected cost associated with the center if EnviroServe wins the dispute. The other unexpected cost is associated with containment at the rifle range, where errant shots or ricochets could endanger a police driver-training track nearby and buildings and people within a half-mile at Springfield Hospital Center. Sam Ecker, the contractor's project manager, and several state law enforcement officials say they questioned the design as early as November 1999 to no avail.

The rifle range has been closed while state officials decide what to do. It and the four pistol ranges were to have opened nine months ago. Though the pistol ranges will open for training in two weeks, according to state officials, why they didn't open sooner is a big part of the dispute between EnviroServe and the state.

EnviroServe, the lowest bidder among six Maryland contractors, signed a construction bid Aug. 18, 1998, but Ecker said two months were lost because the DGS did not grant a "notice to proceed" until Nov. 16, 1998, and then ordered changes in grading and site preparation.

EnviroServe contends that more serious problems surfaced when steel trusses would not support the weight of overhead baffles at the pistol ranges, though they had been built to specifications of the DGS. Baffles are steel plates covered in a fabric that absorbs a bullet's impact.

As a result, Ecker said, thousands of pieces of additional steel bracing had to be cut and welded to the trusses, causing a six-month delay in their installation.